House AYH459 – Site visit 2024-04-19


The walls of the ground-floor extensions have been formed, and the screed poured everywhere that we are using the beam-and-block flooring. In this project, where there is a combination of new and old concrete floors, we opted to install a low-profile underfloor heating system over the insulated screed. This will give us a consistent floor level and heat level throughout, ready for the vinyl flooring.

Upstairs, work is progressing as it can, although there have been some leaks that we are finding hard to pinpoint the origin of.